ICT Project Management quiz
3 questions. No signup. Your move.
What high-level visual plan maps product goals over time?
Now make it a duel.
Play more questions on ICT Project Management in LearnClash. Challenge friends in a new quiz duel.
Play more in the appA tap copies this page’s link so the app can pick up where you left off.
That was every question in this preview. Pick another topic or keep going in the app.
A new quiz every day: Today’s quiz
The video couldn’t load. You can watch it on YouTube.
Choose a topic, answer questions and challenge a friend in LearnClash.
Watch on YouTubeA tap copies this page’s link so the app can pick up where you left off.
More questions about ICT Project Management
These visible examples show the question style. LearnClash turns the full topic into ranked duels and spaced repetition.
-
What is a fixed-length development iteration called in Scrum?
Answer: Sprint
Why: Scrum sprints typically last between one and four weeks, ending with a working product increment regardless of whether every task finished.
-
In Earned Value Management, what formula calculates the Schedule Performance Index?
Answer: EV / PV
Why: An SPI greater than 1.0 indicates project progress is running ahead of the baseline schedule.
-
Which law links work in progress to lead time and throughput?
Answer: Little's Law
Why: Little's Law allows teams to reduce lead times simply by lowering the total work in progress.
-
What does the M in SMART criteria represent?
Answer: Measurable
Why: George T. Doran coined SMART in Management Review in 1981; his M was already measurable, but his A meant assignable and his R realistic.
-
What does an SPI value greater than 1.0 mean for a project schedule?
Answer: Ahead of schedule
Why: Dividing Earned Value by Planned Value yields SPI, where any number above 1.0 shows work is finishing faster than planned.
-
Which contract type places the highest risk on the seller?
Answer: Firm fixed price
Why: The seller absorbs all cost overruns under a firm fixed price agreement, whereas cost-reimbursable models pass expenses to the buyer.